Back to Projects
Sports

Carolina Panthers Training Facility

Led a team of junior engineers through an accelerated construction schedule for a 622,000 sq ft professional sports training complex on a 200-acre site, conducting weekly on-site reviews and resolving field issues in real time.

Location Rock Hill, SC
Size 622,000 sq ft / 200 acres
Sector Sports
Architect Populous
Budget $1 Billion
Role Senior Engineer
Carolina Panthers Rock Hill Development rendering

Image courtesy of Football Stadium Digest / Populous

Overview

The Carolina Panthers Rock Hill Development was envisioned as the team's new headquarters and a world-class regional sports complex on a 200-acre site. Designed by Populous, the $1 billion facility encompassed new headquarters offices, an indoor practice facility, outdoor practice fields, and a pavilion with two 80-foot tall operable glazed doors that could open to integrate indoor and outdoor spaces for events, concerts, and championship games.

The design drew inspiration from South Carolina quarries and Rock Hill's local character, with canted glass walls, articulated metal panels, and LED displays at the entrance, culminating in peaked rooflines.

My Role

  • Organized and led a team of junior engineers to review shop drawings and respond to RFIs under an accelerated construction schedule, ensuring high-quality and timely deliverables.
  • Conducted weekly on-site reviews and coordination to resolve field issues promptly.
  • Collaborated with the construction manager and architect to develop solutions that met schedule and budget constraints.
  • Created lateral analysis models to track load paths and developed spreadsheets to combine gravity and lateral forces for member design.
  • Prepared structural drawings and tonnage reports from schematic through construction phase documents.

Key Outcomes

  • Delivered all structural packages on schedule despite the accelerated timeline.
  • Resolved field issues in real time through weekly site visits, minimizing construction delays.
  • Developed collaborative solutions with the CM and architect that maintained budget while meeting structural requirements.

Skills & Tools

Team Leadership Accelerated Schedule Field Coordination Budget Management RFI Management SAP2000 RAM